CompTIA Project+ (PK0-004) — Question 229
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Answer options
- A. Project manager and project scheduler
- B. Project coordinator and project sponsor
- C. Project champion and project scheduler
- D. Project stakeholders and project team
Correct answer: D
Explanation
The correct answer is D because project stakeholders and the project team are directly involved and impacted by the project's milestones. Options A, B, and C include roles that may need to know but do not encompass the broader audience that is significantly affected by milestone achievements.