Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?
Answer options
- A. Supply Ann with the requested tablet.
- B. Have Ann submit a change request.
- C. Provide Ann with a copy of the project management plan.
- D. Inform Ann that she will receive what has been authorized.
Correct answer: B
Explanation
The correct step is to have Ann submit a change request, as this formalizes her request for a different device and ensures proper documentation and approval processes are followed. Simply supplying the tablet or providing project documents does not address the need for a change in project scope, while informing her of the authorized equipment does not fulfill her request.