An organization recently restructured. Leaders feel they are not in a position to sign off on a required change, which is delaying a project.
Which of the following is the obstacle?

Answer options

Correct answer: A

Explanation

The correct answer is A because the lack of clarity regarding who has the authority to provide approval is directly impacting the project's progress. Options B, C, and D do not specifically address the issue of approval authority, which is the core problem affecting the project timeline.