CompTIA Project+ (PK0-004) — Question 217
Top-level managers are considering joining certain projects, programs, and operations to be managed as a group.
Which of the following is being considered?
Answer options
- A. Organizational changes
- B. PMO establishments
- C. Project interdependencies
- D. Program development
Correct answer: A
Explanation
The correct answer is A, as organizational changes involve restructuring how projects and programs are grouped and managed. Options B and D focus on establishment and development aspects, while C relates to the relationships between projects rather than the management structure itself.