CompTIA Project+ (PK0-004) — Question 220

A project to implement Voice over Internet Protocol for a contact center has been expanded to include the entire organization.
Which of the following BEST describes the constraints involved?

Answer options

Correct answer: D

Explanation

The correct answer is D because resources, requirements, and scope are critical constraints that affect project management and execution, especially in a large-scale implementation. Options A, B, and C do not encompass the unique challenges that arise when expanding the project to the entire organization, making them less suitable in this context.