A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?
Answer options
- A. Quality
- B. Regulations
- C. Schedule
- D. project team
Correct answer: C
Explanation
When project scope changes occur without an increase in budget, the schedule is often affected as additional time may be needed to accommodate the new requirements. Quality may also be impacted, but the most direct consequence of scope changes is typically an alteration to the project schedule. Regulations and the project team are less likely to be directly affected by changes in scope alone.