CompTIA Project+ (PK0-004) — Question 205

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

Answer options

Correct answer: B

Explanation

The first step in developing a project schedule is to add the start and finish dates, as they provide a framework for the entire timeline. Adding durations, tasks, or resources comes after establishing these key dates, which guide the scheduling process.