CompTIA Project+ (PK0-004) — Question 205
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?
Answer options
- A. Add durations.
- B. Add the start and finish dates
- C. Add tasks.
- D. Add resources.
Correct answer: B
Explanation
The first step in developing a project schedule is to add the start and finish dates, as they provide a framework for the entire timeline. Adding durations, tasks, or resources comes after establishing these key dates, which guide the scheduling process.