CompTIA Project+ (PK0-004) — Question 203

The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur.
Which of the following will assist the project team with building the schedule?

Answer options

Correct answer: B

Explanation

Task predecessors are crucial for establishing when tasks can be scheduled because they identify which tasks must be completed before others can begin. While task sequencing, dependencies, and prioritizing are important, they do not provide the specific information about which tasks must precede others in the schedule.