CompTIA Project+ (PK0-004) — Question 182

One of the tasks on a project's critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines.
Which of the following roles has the responsibility of resolving the issue?

Answer options

Correct answer: B

Explanation

The PMO (Project Management Office) is responsible for overseeing project management processes and resources, making them the right choice to resolve conflicts affecting critical path tasks. The CCB (Change Control Board) focuses on changes in project scope, while the Project sponsor provides support and funding, and the Project scheduler manages timelines but does not resolve resource conflicts directly.