CompTIA Project+ (PK0-004) — Question 181

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
Which of the following steps of the control was missed?

Answer options

Correct answer: D

Explanation

The correct answer is D because evaluating the impact and justification of the change is crucial to understanding how it will affect the project. Without this evaluation, the project manager may proceed with a change that could lead to unforeseen consequences. The other options, while important, do not address the critical assessment of the change's implications.