CompTIA Project+ (PK0-004) — Question 183
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks -
A, B, F: 8 weeks -
D, E, H: 12 weeks -
D, B, F: 7 weeks -
Which of the following tasks are on the critical path?
Answer options
- A. A, C, G
- B. A, B, F
- C. D, E, H
- D. D, B, F
Correct answer: C
Explanation
The critical path is the longest path through the network diagram, which determines the shortest time to complete the project. In this case, the path D, E, H has a duration of 12 weeks, making it the critical path, while the other options have shorter durations and are not critical.