CompTIA Project+ (PK0-004) — Question 175

The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)

Answer options

Correct answer: A, E

Explanation

The issue log is critical as it documents conflicts and problems with the vendor, providing concrete reasons for their replacement. The change management plan is also relevant as it outlines the process needed to facilitate the vendor's removal, ensuring stakeholders understand the steps involved. The other options do not directly address the vendor's performance or the necessary actions for their dismissal.