CompTIA Project+ (PK0-004) — Question 176
A project manager is creating the WBS.
In which of the following phases is the project?
Answer options
- A. Initiation
- B. Planning
- C. Execution
- D. Closing
Correct answer: B
Explanation
The project manager is in the Planning phase when creating the Work Breakdown Structure (WBS), as this is a crucial part of project planning that helps in organizing tasks. The Initiation phase focuses on defining the project, Execution involves carrying out the work, and Closing wraps up the project, none of which involve developing the WBS.