CompTIA Project+ (PK0-004) — Question 174
׀ new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
Answer options
- A. Identify and document the risk.
- B. Evaluate the impact and justification.
- C. Implement the change.
- D. Update the documents and plans.
Correct answer: D
Explanation
The correct answer is D because updating documents and plans is typically done after changes have been implemented to reflect the new state of the project. Options A, B, and C are all preliminary steps that need to be completed before any documentation is finalized.