CompTIA Project+ (PK0-004) — Question 168
A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
Answer options
- A. Vendors
- B. Key stakeholders
- C. Resources
- D. Project team
- E. Business analysts
Correct answer: D
Explanation
The Project team is the most relevant audience for a review of the execution phase as they are directly involved in the project's daily activities and can provide insights and feedback. Vendors, key stakeholders, resources, and business analysts, while important, are not as directly engaged in the execution details and may not benefit as much from this specific review.