CompTIA Project+ (PK0-004) — Question 167
An approved change was implemented. Which of the following should be accomplished NEXT?
Answer options
- A. Update the documentation.
- B. Validate the change.
- C. Update the project sponsor.
- D. Validate the impact.
Correct answer: A
Explanation
Updating the documentation is crucial after implementing a change to ensure all records reflect the current state of the project. While validating the change and assessing its impact are important, these activities typically occur before or during the change implementation, not immediately after. Informing the project sponsor is also necessary, but it is a step that can follow documentation updates.