CompTIA Project+ (PK0-004) — Question 167

An approved change was implemented. Which of the following should be accomplished NEXT?

Answer options

Correct answer: A

Explanation

Updating the documentation is crucial after implementing a change to ensure all records reflect the current state of the project. While validating the change and assessing its impact are important, these activities typically occur before or during the change implementation, not immediately after. Informing the project sponsor is also necessary, but it is a step that can follow documentation updates.