CompTIA Project+ (PK0-004) — Question 166

A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)

Answer options

Correct answer: A, C

Explanation

Updating the project charter to include the functional manager as a key stakeholder (Option A) ensures they are recognized in the project's governance. Reviewing the communications plan (Option C) is crucial to verify that the functional manager will be kept informed. Options B, D, and E do not directly address the need for stakeholder recognition and proper communication management.