CompTIA Project+ (PK0-004) — Question 169

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.
The constraint described in this scenario is:

Answer options

Correct answer: C

Explanation

The correct answer is 'scope' because the project was halted due to changing strategic priorities, which directly affects the project's objectives and deliverables. The other options, such as cost, environmental, and scheduling, do not directly relate to the reason for the project's cessation in this scenario.