CompTIA Project+ (PK0-004) — Question 162

The design activity of a project has the following cost attributes:

PV = 100,000 -

EV = 20,000 -

AC = 90,000 -
Based on this scenario, calculate the schedule variance.

Answer options

Correct answer: A

Explanation

The schedule variance (SV) is calculated as SV = EV - PV. In this case, SV = 20,000 - 100,000, which results in −80,000, indicating the project is behind schedule. The other options do not accurately reflect this calculation.