CompTIA Project+ (PK0-004) — Question 162
The design activity of a project has the following cost attributes:
PV = 100,000 -
EV = 20,000 -
AC = 90,000 -
Based on this scenario, calculate the schedule variance.
Answer options
- A. גˆ’80,000
- B. גˆ’70,000
- C. 10,000
- D. 120,000
Correct answer: A
Explanation
The schedule variance (SV) is calculated as SV = EV - PV. In this case, SV = 20,000 - 100,000, which results in −80,000, indicating the project is behind schedule. The other options do not accurately reflect this calculation.