A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?
Answer options
- A. Reduced quality
- B. Reduced scope
- C. Reduced risk
- D. Reduced timeline
Correct answer: A
Explanation
The correct answer is A, as interns typically have less experience, which can lead to a decrease in the quality of work produced. The other options do not directly correlate with the potential challenges posed by less experienced team members; scope, risk, and timeline may not inherently change just because interns are involved.