CompTIA Project+ (PK0-004) — Question 160
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale.
Which of the following is the MOST likely reason the project manager would be unaware of the team member's decreased morale?
Answer options
- A. The project manager did not pay attention to visual cues.
- B. The project manager did not perform active listening.
- C. The project manager did not prioritize team member concerns.
- D. The project manager did not visit the project's international office locations.
Correct answer: D
Explanation
The correct answer is D because visiting international office locations allows the project manager to directly observe team dynamics and morale. While options A, B, and C may contribute to a lack of awareness, they are less likely to be the primary reason compared to the absence of physical presence at different locations, which provides firsthand insight into team sentiment.