CompTIA Project+ (PK0-004) — Question 159
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
Answer options
- A. Individually call all project team members.
- B. Send an email to all project team members.
- C. Schedule a conference call.
- D. Schedule a face-to-face meeting.
Correct answer: C
Explanation
Scheduling a conference call (C) is the most effective way to quickly communicate critical information to a large team, ensuring immediate feedback and discussion. Individually calling all team members (A) is time-consuming, sending an email (B) may lead to delays in response, and a face-to-face meeting (D) is impractical for a global team, making them less suitable options.