CompTIA Project+ (PK0-004) — Question 159

A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?

Answer options

Correct answer: C

Explanation

Scheduling a conference call (C) is the most effective way to quickly communicate critical information to a large team, ensuring immediate feedback and discussion. Individually calling all team members (A) is time-consuming, sending an email (B) may lead to delays in response, and a face-to-face meeting (D) is impractical for a global team, making them less suitable options.