CompTIA Project+ (PK0-004) — Question 158
Which of the following information does the project risk register typically contain?
Answer options
- A. Type of risk, identified risk, risk response, impact of risk, severity of risk
- B. Type of risk, project task, risk response, impact of risk, severity of risk
- C. Type of risk, identified risk, risk response, project schedule risk, severity of risk
- D. Type of risk, identified risk, risk response, impact of risk, risk avoidance
Correct answer: B
Explanation
The correct answer is B, as the project risk register typically includes the type of risk, project task, risk response, impact of risk, and severity of risk. Options A and C contain 'identified risk' and 'project schedule risk' respectively, which are not standard components of a risk register. Option D includes 'risk avoidance' instead of a project task, making it incorrect as well.