CompTIA Project+ (PK0-004) — Question 163
A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the
MOST likely reason for the failed inspection?
Answer options
- A. There were insufficient resources assigned to the task.
- B. The prior document version was not reviewed.
- C. Version control processes were not applied.
- D. The CCB was not contacted.
Correct answer: C
Explanation
The failed inspection is most likely due to the lack of version control processes being applied, which would have ensured that all updates and changes were tracked and managed properly. Without version control, discrepancies between document versions could lead to confusion and errors in the project deliverables. The other options, while potentially contributing factors, do not directly address the critical need for managing document versions in this scenario.