CompTIA Project+ (PK0-004) — Question 139
A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take
FIRST?
Answer options
- A. Submit a change request to the CCB.
- B. Implement the change to the project.
- C. Determine the impact of the requested change.
- D. Update the schedule to accommodate the change.
Correct answer: C
Explanation
The correct first step is to assess the ramifications of the proposed change, as understanding the impact on the project is crucial before any further actions are taken. Submitting a change request (A), implementing the change (B), or updating the schedule (D) should only occur after evaluating how the change will affect the project scope, timeline, and resources.