CompTIA Project+ (PK0-004) — Question 139

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take
FIRST?

Answer options

Correct answer: C

Explanation

The correct first step is to assess the ramifications of the proposed change, as understanding the impact on the project is crucial before any further actions are taken. Submitting a change request (A), implementing the change (B), or updating the schedule (D) should only occur after evaluating how the change will affect the project scope, timeline, and resources.