Which of the following includes setting governance gates as well as predecessors and dependencies?

Answer options

Correct answer: D

Explanation

The correct answer is D, Project scheduling, because it encompasses the planning of tasks, including governance gates, predecessors, and dependencies. The other options do not specifically address the organization of tasks in relation to time and order, which is fundamental to scheduling.