CompTIA Project+ (PK0-004) — Question 138
Which of the following includes setting governance gates as well as predecessors and dependencies?
Answer options
- A. Project communication
- B. Project constraints
- C. Project change control
- D. Project scheduling
Correct answer: D
Explanation
The correct answer is D, Project scheduling, because it encompasses the planning of tasks, including governance gates, predecessors, and dependencies. The other options do not specifically address the organization of tasks in relation to time and order, which is fundamental to scheduling.