CompTIA Project+ (PK0-004) — Question 137
When developing a project schedule, which of the following resources is the BEST to estimate task duration?
Answer options
- A. Project manager
- B. Project scheduler
- C. Project team
- D. Project sponsor
Correct answer: C
Explanation
The Project team is the most suitable choice for estimating task duration because they possess the detailed knowledge and expertise about the tasks involved. While the Project manager, Project scheduler, and Project sponsor have important roles, they may not have the comprehensive understanding of the specific tasks required to provide accurate estimates.