CompTIA Project+ (PK0-004) — Question 140

A project sponsor informs the project manager that the project completion date must be moved one month earlier. Which of the following should the project manager do NEXT?

Answer options

Correct answer: B

Explanation

The correct answer is B because the project manager needs to first communicate the impact of the new deadline to stakeholders and the sponsor. This allows for transparency and ensures that everyone is aware of the changes in schedule and cost. The other options involve actions that would be taken after informing stakeholders, such as recalculating paths or resource needs.