CompTIA Project+ (PK0-004) — Question 132

Which of the following is a component of the project cost control?

Answer options

Correct answer: B

Explanation

The burn rate is a crucial aspect of project cost control as it measures the rate at which budgeted funds are spent over time. The other options, such as the scope statement, MOU, and SLA, pertain to project planning and agreements rather than direct cost management.