A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the following options would be MOST useful to the project manager to accommodate the new scope without extending the completion date? (Choose two.)

Answer options

Correct answer: A, D

Explanation

The correct answers, A and D, are effective strategies for managing increased scope without extending the deadline. Fast-tracking tasks helps to optimize the schedule, while requesting additional funds allows for acquiring more resources to handle the new workload. The other options either do not effectively address the issue or may lead to unfavorable project outcomes.