CompTIA Project+ (PK0-004) — Question 133

A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:

Answer options

Correct answer: C

Explanation

The correct answer is C, RFI (Request for Information), as it is used to gather information from suppliers about their products or services when the project manager needs to understand unfamiliar technology. The other options, such as RTM (Requirements Traceability Matrix), RFQ (Request for Quotation), and RFP (Request for Proposal), serve different purposes and are not primarily focused on information gathering about new technologies.