CompTIA Project+ (PK0-004) — Question 126
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:
Answer options
- A. durations.
- B. tasks.
- C. critical path.
- D. resources.
Correct answer: B
Explanation
The project team should first identify the tasks, as these are the specific activities that need to be completed to achieve the project goals. Without knowing the tasks, it is impossible to determine durations, resources, or the critical path accurately.