CompTIA Project+ (PK0-004) — Question 125
A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?
Answer options
- A. Project schedule
- B. Project management plan
- C. Project charter
- D. Staffing matrix
Correct answer: B
Explanation
The correct answer is B, as the Project Management Plan includes the resource management plan, which details the project manager's authority regarding resource assignments. The Project Schedule (A) outlines timelines, while the Project Charter (C) provides high-level project information, and the Staffing Matrix (D) focuses on resource allocation without authority specifics.