CompTIA Project+ (PK0-004) — Question 127

A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks. This is an example of:

Answer options

Correct answer: C

Explanation

The correct answer is C, task reassignment, as the project manager is redistributing tasks to manage the workload better. While outsourcing (B) involves hiring another organization for work, in this scenario, the focus is specifically on reallocating tasks within the project. Crashing (A) refers to adding resources to speed up tasks, and relocation (D) does not apply in this context.