CompTIA Project+ (PK0-004) — Question 118

A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

Answer options

Correct answer: B

Explanation

The correct answer is B, key stakeholders, because they have a vested interest in the project's outcome and need to be kept informed of any risks that arise. Options A, C, and D are less critical as they do not encompass all parties who might need to understand the implications of the realized risk.