A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?

Answer options

Correct answer: A

Explanation

The Requirements traceability matrix is essential for ensuring that all specified deliverables are accounted for and helps track changes to prevent scope creep. In contrast, a Gantt chart primarily focuses on scheduling, a SWOT analysis assesses strengths and weaknesses, and a project charter outlines the project but does not manage scope directly.