CompTIA Project+ (PK0-004) — Question 116
Which of the following should be included in an effective SOW?
Answer options
- A. Lessons learned
- B. Procurement process
- C. Corrective action plan
- D. Project objectives
Correct answer: C
Explanation
A Corrective action plan is crucial in an SOW as it outlines how to address any issues that may arise during the project. While lessons learned, the procurement process, and project objectives are important, they do not specifically address the management of potential problems, which is the primary focus of a corrective action plan.