Scrum Master Certified (SMC) — Question 33

Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have gathered together to create the Project Vision. They are trying to determine and document the difference between current business capabilities and the final desired set of capabilities. Which one of the following should they use to arrive at a conclusive decision?

Answer options

Correct answer: C

Explanation

Gap Analysis is the most appropriate method for identifying the differences between current capabilities and desired outcomes, making it the correct choice. Trial Projects and JAD Sessions focus on different aspects of project management and collaboration, while SWOT Analysis evaluates strengths, weaknesses, opportunities, and threats, which is not specifically aimed at capability assessment.