Scrum Master Certified (SMC) — Question 32
Emily has taken on the role of Scrum Master on a new project. Training the team is one of her major responsibilities. As Scrum Master, which aspects will Emily need to address in this respect?
A) Gaps in technical knowledge in any of the team members.
B) Shortcomings in the Scrum Team's understanding of business value of features.
C) Increasing the team's capability to articulate their challenges to find solutions.
D) Lack of understanding of the Scrum processes and principles.
Answer options
- A. B and C
- B. A, B, and C
- C. C only
- D. C and D
Correct answer: D
Explanation
The correct answer is D because understanding the Scrum processes and principles is crucial for the team to function effectively, and the ability to express challenges helps in finding solutions. While technical knowledge and business value are important, they are not as foundational to the Scrum framework as the processes and principles.