Scrum Master Certified (SMC) — Question 18
Which of the following statements about non-core Scrum roles is correct?
Answer options
- A. Non-core roles are mandatorily required for the Scrum project to be successful.
- B. Non-core roles are supportive roles indirectly responsible for the success or failure of the project.
- C. Non-core roles are involved with the project, but do not have any interest in the project.
- D. Non-core roles have a formal stature on the project team and are continuously involved in the Scrum process.
Correct answer: A
Explanation
The correct answer is A because non-core roles are not strictly necessary for a Scrum project's success; they provide support rather than being mandatory. Options B, C, and D misrepresent the nature of non-core roles, as they do not imply a formal requirement or direct accountability for project success.