Scrum Master Certified (SMC) — Question 17
You are the Scrum Master on a project to develop machine parts for automobile manufacturing. The Product Owner on your project proposes to use Utility
Function to find out the stakeholders' risk tolerance level. Which of the following is NOT a risk tolerance classification?
Answer options
- A. Risk Averter.
- B. Risk Seeker.
- C. Risk Mitigator.
- D. Neutral Risk Taker.
Correct answer: C
Explanation
The correct answer is C, Risk Mitigator, as it does not classify risk tolerance but rather describes a strategy to manage risk. The other options, Risk Averter, Risk Seeker, and Neutral Risk Taker, are established classifications that define how individuals or stakeholders approach risk.