LEED Green Associate (LEED GA) — Question 22
Which of the following strategies prioritizes cost-effectiveness when designing a LEED project?
Answer options
- A. Onsite renewable systems
- B. Enhanced Commissioning (Cx)
- C. Measuring and verifying systems performance for one year
- D. Applying an integrative design process
Correct answer: D
Explanation
The correct answer, D, highlights the importance of an integrative design process that considers all aspects of the project from the beginning, leading to cost savings. Options A, B, and C may contribute to sustainability but do not specifically focus on maximizing cost-effectiveness in the overall project design.