LEED Green Associate (LEED GA) — Question 21
The project team is conducting a feasibility study of a building project. The developer has pre-qualified four potential sites that are all financially viable. Within the context of LEED, which site is the most applicable?
Answer options
- A. A brownfield site with no access to metro
- B. A brownfield site in a national park with car access only
- C. A greenfield site with access to public transport and proximity to grocery stores
- D. A brownfield site with access to five lines of public transportation and basic services
Correct answer: D
Explanation
The correct answer is D because it offers significant public transportation access and essential services, aligning with LEED's emphasis on sustainable site selection. Options A and B lack adequate public transport options, and while C is a greenfield site with some amenities, it does not provide the same level of transport accessibility as option D.