TOGAF Enterprise Architecture Practitioner — Question 64

What is an objective of the ADM Implementation Governance Phase?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the importance of making sure that the target architecture aligns with established standards and requirements. Options B, C, and D, while relevant to the overall governance process, do not specifically focus on the conformance aspect which is critical during the Implementation Governance Phase.