TOGAF Enterprise Architecture Practitioner — Question 62

What are the following activities part of?

• Risk classification
• Risk identification
• Initial risk assessment

Answer options

Correct answer: B

Explanation

The correct answer is B, Risk Management, as it encompasses the processes of risk classification, identification, and initial assessment. The other options, such as Phase G and Phase A, refer to specific phases in project management frameworks, while Security Architecture does not specifically address risk management activities.