ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 88
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)
Answer options
- A. Track actual amount spent compared to an approved budget.
- B. Configure cost type definition.
- C. Determine overall project cost requirements.
- D. Define target for the portfolio.
- E. Establish resource requirements and track costs.
Correct answer: A, C, E
Explanation
The correct answers, A, C, and E, relate directly to financial oversight and resource management, which are core functions of the PPM Standard plugin. Options B and D focus on configuration and goal-setting, which are not primary activities facilitated by this plugin.