ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 84
Which conditions must be met in order to change the planned start date of a project? (Choose two.)
Answer options
- A. project_funding records are selected for execution
- B. Project actual dates are not populated
- C. The state of a project is Pending or Open
- D. The state of the project is Closed Skipped
Correct answer: B, C
Explanation
To change the planned start date, the project must not have actual dates recorded, ensuring that no work has been done that would lock in those dates. Additionally, the project state must be either Pending or Open, as a Closed Skipped state indicates the project is finalized and cannot be altered.