ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 84

Which conditions must be met in order to change the planned start date of a project? (Choose two.)

Answer options

Correct answer: B, C

Explanation

To change the planned start date, the project must not have actual dates recorded, ensuring that no work has been done that would lock in those dates. Additionally, the project state must be either Pending or Open, as a Closed Skipped state indicates the project is finalized and cannot be altered.