ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 46

When creating a program, which of the following cannot be part of multiple programs? (Choose two.)

Answer options

Correct answer: C, D

Explanation

The correct answers are C and D because a Project and Demand are unique to a specific program and cannot be shared across multiple programs. In contrast, Tasks and Portfolio can be part of various programs, as they are not exclusive.