ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 39
Using the Request type field on a resource plan, which options can be used to request a resource? (Choose three.)
Answer options
- A. Day
- B. Person Days
- C. Hours
- D. FTE
- E. Month
Correct answer: B, C, D
Explanation
The correct answers are B, C, and D because 'Person Days', 'Hours', and 'FTE' (Full-Time Equivalent) are all valid units for requesting resources in a resource plan. 'Day' and 'Month' do not represent specific measurable units for resource allocation in this context.