ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 38
Which of the following is the default schedule for the Project Management application?
Answer options
- A. Repeats every week on weekdays Monday through Friday. Includes the child schedule U.S. Holidays.
- B. Repeats every week on weekdays Monday through Friday from 8:00am to noon and 1:00-5:00pm.
- C. Repeats every week on weekdays Monday through Friday from 9:00am to 5:00pm.
- D. Repeats every week on weekdays Monday through Friday.
Correct answer: B
Explanation
The correct answer is B, as it specifies the exact hours of operation for the Project Management application, which is from 8:00am to noon and 1:00-5:00pm. Options A, C, and D do not provide the same detailed schedule, making them incorrect as they either lack specific times or include additional elements that don't define the default schedule.